Accurate Reconstruction Point at Galloping Hill. Bldg 251

Accurate Reconstruction Point at Galloping Hill. Bldg 251Accurate Reconstruction Point at Galloping Hill. Bldg 251Accurate Reconstruction Point at Galloping Hill. Bldg 251

Timeline of Activity on Your Project

3/7/26 - Date of fire

3/8/26 - Tom Licciardi of Accurate Reconstruction performed his initial inspection

3/10/26 - Tom performed an additional inspection with GNY's independent adjuster

3/13/26 - Our preliminary estimate was submited to adjuster

3/16/26 - Introductory meeting with homeowners via Zoom

3/23/26 -   Tommy will inspect the property with the Architect on Tuesday, 3/24/2026

4/7/26 -   We have received the architectural drawings and will be submitting permit applications shortly.

5/6/26 - Demolition will begin tomorrow.

5/12/26 -   Thank you for your patience.  We will begin new work as soon as our permit applications are approved by Town Hall

Close-up of a calendar with a pen pointing at the 20th date.

Copyright © 2026 Accurate Reconstruction @ Point at Galloping Hill Bldg 251 - All Rights Reserved.

Powered by

This website uses cookies.

We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

Accept